Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand)
- Item number
- 11.19.4
- Analysis basis
- 10 sqm
- Priced inputs
- 12
- Derived rate
- ₹1,379.00/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.19.4 (Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand) : Ordinary cement without any pigment) is derived from 12 priced inputs for 10 sqm and works out to ₹1,379.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement :
- 4 coarse sand)
- Ordinary cement for
- (i) Cement slurry @ 4.4kg/sqm = 44kg+
- (ii) Grouting = 44 kg.
- Total = 88kg or 0.088 tonne
- Labour & sundries
- [3.08+2.84(for tiles)]
- Less for dark shade pigment
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1229 | MAT | Chequered terrazo tiles 22 mm thick (dark shade) including 10% wastageChequered terrazzo tiles 22 mm thick (dark shade) | sqm | 11 | 280.00 | 3,080.00 |
| 9977 | MAT | Carriage of tiles | L.S. | 40.43 | 2.27 | 91.78 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.088 | 5,156.00 | 453.73 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | 3.08 | 75.00 | 231.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.6 | 816.00 | 1,305.60 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 1 | 816.00 | 816.00 |
| 0101 | LAB | Bhisti | day | 1 | 816.00 | 816.00 |
| 0013 | MACH | Machine for rubbing of floors | day | 1.6 | 350.00 | 560.00 |
| 9999 | MAT | Sundries including pigment wherever required and carborandum stone etc | L.S. | 161.98 | 2.27 | 367.69 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | -5.92 | 75.00 | -444.00 |
- TOTAL
- 9,693.22
- Add 1 % Water charges on “W”
- +96.93
- TOTAL
- 9,790.15
- Add GST on “X” (multiplying factor 0.2127)
- +2,082.36
- TOTAL
- 11,872.51
- Add 15% CPOH on “Y”
- +1,780.88
- TOTAL
- 13,653.39
- Add Cess @ 1% on “Z”
- +136.53
- Cost of 10 sqm.
- 13,789.92
- Cost of 1 sqm.
- 1,378.99
- SAY
- ₹1,379.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 786
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 786. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate