Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand)
- Item number
- 11.19.3
- Analysis basis
- 10 sqm
- Priced inputs
- 11
- Derived rate
- ₹1,442.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.19.3 (Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand) : Dark shade pigment using ordinary cement) is derived from 11 priced inputs for 10 sqm and works out to ₹1,442.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 4 (1 cement :
- 4 coarse sand)
- Ordinary cement for
- (i) Cement slurry @ 4.4kg/sqm = 44kg+
- (ii) Grouting = 44 kg.
- Total = 88kg or 0.088 tonne
- Labour & sundries
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1229 | MAT | Chequered terrazo tiles 22 mm thick (dark shade) including 10% wastageChequered terrazzo tiles 22 mm thick (dark shade) | sqm | 11 | 280.00 | 3,080.00 |
| 9977 | MAT | Carriage of tiles | L.S. | 40.43 | 2.27 | 91.78 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.224 | 4,211.70 | 943.42 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.088 | 5,156.00 | 453.73 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | 3.08 | 75.00 | 231.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.6 | 816.00 | 1,305.60 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 1 | 816.00 | 816.00 |
| 0101 | LAB | Bhisti | day | 1 | 816.00 | 816.00 |
| 0013 | MACH | Machine for rubbing of floors | day | 1.6 | 350.00 | 560.00 |
| 9999 | MAT | Sundries including pigment wherever required and carborandum stone etc | L.S. | 161.98 | 2.27 | 367.69 |
- TOTAL
- 10,137.22
- Add 1 % Water charges on “W”
- +101.37
- TOTAL
- 10,238.59
- Add GST on “X” (multiplying factor 0.2127)
- +2,177.75
- TOTAL
- 12,416.34
- Add 15% CPOH on “Y”
- +1,862.45
- TOTAL
- 14,278.79
- Add Cess @ 1% on “Z”
- +142.79
- Cost of 10 sqm.
- 14,421.58
- Cost of 1 sqm.
- 1,442.16
- SAY
- ₹1,442.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 785
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 785. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.