Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand)

Medium shade pigment using 50% white cement 50% Grey cement
Item number
11.20.2
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹1,328.35/ SQM
D-01/RATE ANALYSISITEM 11.20.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.20.2 (Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand) Medium shade pigment using 50% white cement 50% Grey cement) is derived from 9 priced inputs for 10 sqm and works out to ₹1,328.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Grey cement for slurry @ 4.4kg/sqm.
  • = 44 kg.+
  • grey cement for grouting 2.4kg/sqm. =
  • 24kg.
  • Total = 68 kg
  • White cement for grouting @ 2.4kg/sqm.
  • = 24 kg
ANALYSIS OF RATES · ITEM 11.20.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7237MATPrecast chequered cement tiles 22 mm thick medium shade using 50% white cement, 50% ordinary cement including 10% wastagePrecast chequered cement tiles 22 mm thick medium shade using 50% white cement & 50% ordinary cementsqm11358.003,938.00
9977MATCarriage of tilesL.S.40.432.2791.78
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.224,211.70926.57
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0685,156.00350.61
0368MATWhite Cementtonne0.02410,500.00252.00
0876MATGreen or blue medium shade pigmentkilogram3.0860.00184.80
0124LABMason 2nd classMason 2nd classday1.6816.001,305.60
0115LABCoolieday2736.001,472.00
0101LABBhistiday1816.00816.00
BUILD-UP TO RATE
TOTAL
9,337.36
Add 1 % Water charges on “W”
+93.37
TOTAL
9,430.73
Add GST on “X” (multiplying factor 0.2127)
+2,005.92
TOTAL
11,436.65
Add 15% CPOH on “Y”
+1,715.50
TOTAL
13,152.15
Add Cess @ 1% on “Z”
+131.52
Cost of 10 sqm.
13,283.67
Cost of 1 sqm.
1,328.37
SAY
₹1,328.35
D-02/SOURCEPRINTED PAGE 788
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
788

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 788. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.