Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)

Ordinary cement without any pigment
Item number
11.12.1.6
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹1,832.80/ SQM
D-01/RATE ANALYSISITEM 11.12.1.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.6 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : Ordinary cement without any pigment) is derived from 3 priced inputs for 10 sqm and works out to ₹1,832.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Less cost of dark shade pigment
  • Deduct for
ANALYSIS OF RATES · ITEM 11.12.1.6DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 11.12.1.1 of SH: FlooringRate as per item 11.12.1.1sqm101,864.3018,643.00
0874MATBlack colour dark shade pigmentkilogram-2.8475.00-213.00
9999MATDeduct for Carriage of pigmentL.S.-3.642.27-8.26
BUILD-UP TO RATE
TOTAL
18,421.74
Add 1 % Water charges on “W-A”
-2.21
TOTAL
18,419.53
Add GST on “X-A” (multiplying factor 0.2127)
-47.53
TOTAL
18,372.00
Add 15% CPOH on “Y-A”
-40.65
TOTAL
18,331.35
Add Cess @ 1% on “Z-A”
-3.12
Cost of 10 sqm.
18,328.23
Cost of 1 sqm.
1,832.82
SAY
₹1,832.80
D-02/SOURCEPRINTED PAGE 775
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
775

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.