Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)

Light shade pigment with ordinary cement
Item number
11.12.1.5
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹1,860.25/ SQM
D-01/RATE ANALYSISITEM 11.12.1.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.5 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : Light shade pigment with ordinary cement) is derived from 3 priced inputs for 10 sqm and works out to ₹1,860.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • shade pigment instead of dark shade
  • pigment
  • Add difference of cost due to using Light
  • Add for
  • Deduct for
ANALYSIS OF RATES · ITEM 11.12.1.5DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 11.12.1.1 of SH: FlooringRate as per item 11.12.1.1sqm101,864.3018,643.00
0875MATRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentkilogram2.8465.00184.60
0874MATBlack colour dark shade pigmentkilogram-2.8475.00-213.00
BUILD-UP TO RATE
TOTAL
18,614.60
Add 1 % Water charges on “W-A”
-0.28
TOTAL
18,614.32
Add GST on “X-A” (multiplying factor 0.2127)
-6.10
TOTAL
18,608.22
Add 15% CPOH on “Y-A”
-5.22
TOTAL
18,603.00
Add Cess @ 1% on “Z-A”
-0.40
Cost of 10 sqm.
18,602.60
Cost of 1 sqm.
1,860.26
SAY
₹1,860.25
D-02/SOURCEPRINTED PAGE 774
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
774

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 774. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.