Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)

White cement without any pigment
Item number
11.12.1.4
Analysis basis
100 sqm
Priced inputs
9
Derived rate
₹1,863.60/ SQM
D-01/RATE ANALYSISITEM 11.12.1.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.4 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : White cement without any pigment) is derived from 9 priced inputs for 100 sqm and works out to ₹1,863.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • For under layer of 12mm thick Cement
  • mortar 1:3 (1 cement : 3 coarse sand) for
  • 10sqm = 0.144+
  • Extra for rounding = 0.03
  • Total for 100sqm =0.174 x10 = 1.740
  • Top layer 6mm thick
ANALYSIS OF RATES · ITEM 11.12.1.4DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum1.744,881.958,494.59
0785MATMarble chips upto 4mm and downsize White & blackMarble chips up to 4 mm and down size White & blackquintal8.72200.001,744.00
0368MATWhite Cementtonne0.40510,500.004,252.50
0784MATMarble dust/ powdercum0.071,180.0082.60
0124LABMason 2nd classMason 2nd classday30816.0024,480.00
0114LABBeldarday30736.0022,080.00
0101LABBhistiday10816.008,160.00
0139LABSkilled Beldar (for floor rubbing etc.)day70816.0057,120.00
9999MATSundriesL.S.2,018.92.274,582.90
BUILD-UP TO RATE
TOTAL
1,30,996.59
Add 1 % Water charges on “W”
+1,309.97
TOTAL
1,32,306.56
Add GST on “X” (multiplying factor 0.2127)
+28,141.61
TOTAL
1,60,448.17
Add 15% CPOH on “Y”
+24,067.23
TOTAL
1,84,515.40
Add Cess @ 1% on “Z”
+1,845.15
Cost of 100 sqm.
1,86,360.55
Cost of 1 sqm.
1,863.61
SAY
₹1,863.60
D-02/SOURCEPRINTED PAGE 774
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
774

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 774. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.