Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)
- Item number
- 11.12.1.4
- Analysis basis
- 100 sqm
- Priced inputs
- 9
- Derived rate
- ₹1,863.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.4 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : White cement without any pigment) is derived from 9 priced inputs for 100 sqm and works out to ₹1,863.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- For under layer of 12mm thick Cement
- mortar 1:3 (1 cement : 3 coarse sand) for
- 10sqm = 0.144+
- Extra for rounding = 0.03
- Total for 100sqm =0.174 x10 = 1.740
- Top layer 6mm thick
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8 | cum | 1.74 | 4,881.95 | 8,494.59 | |
| 0785 | MAT | Marble chips upto 4mm and downsize White & blackMarble chips up to 4 mm and down size White & black | quintal | 8.72 | 200.00 | 1,744.00 |
| 0368 | MAT | White Cement | tonne | 0.405 | 10,500.00 | 4,252.50 |
| 0784 | MAT | Marble dust/ powder | cum | 0.07 | 1,180.00 | 82.60 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 30 | 816.00 | 24,480.00 |
| 0114 | LAB | Beldar | day | 30 | 736.00 | 22,080.00 |
| 0101 | LAB | Bhisti | day | 10 | 816.00 | 8,160.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 70 | 816.00 | 57,120.00 |
| 9999 | MAT | Sundries | L.S. | 2,018.9 | 2.27 | 4,582.90 |
- TOTAL
- 1,30,996.59
- Add 1 % Water charges on “W”
- +1,309.97
- TOTAL
- 1,32,306.56
- Add GST on “X” (multiplying factor 0.2127)
- +28,141.61
- TOTAL
- 1,60,448.17
- Add 15% CPOH on “Y”
- +24,067.23
- TOTAL
- 1,84,515.40
- Add Cess @ 1% on “Z”
- +1,845.15
- Cost of 100 sqm.
- 1,86,360.55
- Cost of 1 sqm.
- 1,863.61
- SAY
- ₹1,863.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 774
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 774. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.