Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand)
- Item number
- 11.12.1.3
- Analysis basis
- 100 sqm
- Priced inputs
- 5
- Derived rate
- ₹1,873.65/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.12.1.3 (Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : Medium shade pigment with 50% white cement and 50% ordinary cement) is derived from 5 priced inputs for 100 sqm and works out to ₹1,873.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- um shade pigment instead of dark shade
- pigment
- cement instead of grey cement
- Add difference of cost due to using medi-
- Add for
- Deduct for
- Add Difference of cost due to using white
- Add for
- Deduct for
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 11.12.1.1 of SH:FlooringRate as per item 11.12.1.1 | sqm | 100 | 1,864.30 | 1,86,430.00 | |
| 0876 | MAT | Green or blue medium shade pigment | kilogram | 28.4 | 60.00 | 1,704.00 |
| 0874 | MAT | Black colour dark shade pigment | kilogram | -28.4 | 75.00 | -2,130.00 |
| 0368 | MAT | White Cement | tonne | 0.203 | 10,500.00 | 2,131.50 |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | -0.203 | 5,156.00 | -1,046.67 |
- TOTAL
- 1,87,088.83
- Add 1 % Water charges on “W-A”
- +6.59
- TOTAL
- 1,87,095.42
- Add GST on “X-A” (multiplying factor 0.2127)
- +141.53
- TOTAL
- 1,87,236.95
- Add 15% CPOH on “Y-A”
- +121.04
- TOTAL
- 1,87,357.99
- Add Cess @ 1% on “Z-A”
- +9.28
- Cost of 100 sqm.
- 1,87,367.27
- Cost of 1 sqm.
- 1,873.67
- SAY
- ₹1,873.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 773
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 773. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.