Providing and fixing glass strips in joints of terrazo/ cement concrete floors

40 mm wide and 4 mm thick
Item number
11.13.1
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹91.75/ METRE
D-01/RATE ANALYSISITEM 11.13.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.13.1 (Providing and fixing glass strips in joints of terrazo/ cement concrete floors 40 mm wide and 4 mm thick) is derived from 5 priced inputs for 10 metre and works out to ₹91.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Glass strips = 10m
  • Total = 11m
  • Add 10% for wastage = 1m
ANALYSIS OF RATES · ITEM 11.13.1DETAILS OF COST FOR 10 METRE LENGTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1149MATGlass strip 4 mm thick40 mm deepGlass strip 4 mm thick 40 mm deepmetre1120.00220.00
9977MATCarriage of glassL.S.2.732.276.20
0124LABMason 2nd classMason 2nd classday0.25816.00204.00
0114LABBeldarday0.25736.00184.00
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
644.89
Add 1 % Water charges on “W”
+6.45
TOTAL
651.34
Add GST on “X” (multiplying factor 0.2127)
+138.54
TOTAL
789.88
Add 15% CPOH on “Y”
+118.48
TOTAL
908.36
Add Cess @ 1% on “Z”
+9.08
Cost of 10 metre
917.44
Cost of 1 metre
91.74
SAY
₹91.75
D-02/SOURCEPRINTED PAGE 775
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
775

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.