Providing and fixing glass strips in joints of terrazo/ cement concrete floors
- Item number
- 11.13.1
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹91.75/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.13.1 (Providing and fixing glass strips in joints of terrazo/ cement concrete floors 40 mm wide and 4 mm thick) is derived from 5 priced inputs for 10 metre and works out to ₹91.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Glass strips = 10m
- Total = 11m
- Add 10% for wastage = 1m
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1149 | MAT | Glass strip 4 mm thick40 mm deepGlass strip 4 mm thick 40 mm deep | metre | 11 | 20.00 | 220.00 |
| 9977 | MAT | Carriage of glass | L.S. | 2.73 | 2.27 | 6.20 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.25 | 816.00 | 204.00 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 644.89
- Add 1 % Water charges on “W”
- +6.45
- TOTAL
- 651.34
- Add GST on “X” (multiplying factor 0.2127)
- +138.54
- TOTAL
- 789.88
- Add 15% CPOH on “Y”
- +118.48
- TOTAL
- 908.36
- Add Cess @ 1% on “Z”
- +9.08
- Cost of 10 metre
- 917.44
- Cost of 1 metre
- 91.74
- SAY
- ₹91.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 775
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.