CPWD Analysis of Rates · Finishing
Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping, sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete
- Item number
- 13.91
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 5
- Derived rate
- ₹25.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.91 — Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping, sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete — is derived from 5 priced inputs for 10 sqm and works out to ₹25.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.11 | 736.00 | 80.96 |
| 0115 | CoolieLabour | day | 0.05 | 736.00 | 36.80 |
| 0101 | BhistiLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Scrapper, sand paper etc.Material | L.S. | 6.24 | 2.27 | 14.16 |
| 9999 | Sundries including mortar to repair the surfaceMaterial | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 176.85
- Add 1 % Water charges on “W”
- 1.77
- TOTAL
- 178.62
- Add GST on “X” (multiplying factor 0.2127)
- 37.99
- TOTAL
- 216.61
- Add 15% CPOH on “Y”
- 32.49
- TOTAL
- 249.10
- Add Cess @ 1% on “Z”
- 2.49
- Cost of 10 sqm.
- 251.59
- Cost of 1 sqm.
- 25.16
- Say
- 25.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1016. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.