Painting on G.S. sheet with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade

Old work (one or more coats)
Item number
13.92.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹93.30/ SQM
D-01/RATE ANALYSISITEM 13.92.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.92.1 (Painting on G.S. sheet with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : Old work (one or more coats)) is derived from 6 priced inputs for 10 sqm and works out to ₹93.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.92.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0845MATRoofing paint for iron sheets in red colourlitre0.46135.0062.10
9977MATCarriageL.S.0.522.271.18
0131LABPainterday0.36816.00293.76
0115LABCoolieday0.36736.00264.96
9999MATPutty, brushes sand paper etc.L.S.6.762.2715.35
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
655.65
Add 1 % Water charges on “W”
+6.56
TOTAL
662.21
Add GST on “X” (multiplying factor 0.2127)
+140.85
TOTAL
803.06
Add 15% CPOH on “Y”
+120.46
TOTAL
923.52
Add Cess @ 1% on “Z”
+9.24
Cost of 10 sqm.
932.76
Cost of 1 sqm.
93.28
SAY
₹93.30
D-02/SOURCEPRINTED PAGE 1017
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1017

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1017. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.