CPWD Analysis of Rates · Finishing
Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement
20 mm cement plaster
- Item number
- 13.9.2
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 9
- Derived rate
- ₹587.20 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.9.2 — Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement 20 mm cement plaster — is derived from 9 priced inputs for 10 sqm and works out to ₹587.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3 (1 cement : 3 coarse
- sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.224 | 4,881.95 | 1,093.56 | |
| 0155 | Mason (average)Labour | day | 0.94 | 857.00 | 805.58 |
| 0115 | CoolieLabour | day | 1.02 | 736.00 | 750.72 |
| 0101 | BhistiLabour | day | 1.1 | 816.00 | 897.60 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 12.61 | 2.27 | 28.62 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.02 | 5,156.00 | 103.12 |
| 0155 | Mason (average)Labour | day | 0.27 | 857.00 | 231.39 |
| 0115 | CoolieLabour | day | 0.27 | 736.00 | 198.72 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 4,127.61
- Add 1 % Water charges on “W”
- 41.28
- TOTAL
- 4,168.89
- Add GST on “X” (multiplying factor 0.2127)
- 886.72
- TOTAL
- 5,055.61
- Add 15% CPOH on “Y”
- 758.34
- TOTAL
- 5,813.95
- Add Cess @ 1% on “Z”
- 58.14
- Cost of 10.00 sqm
- 5,872.09
- Cost of 1.00 sqm
- 587.21
- Say
- 587.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 962. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.