15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement on the rough side of single or half brick wall

Item number
13.10
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹506.60/ SQM
D-01/RATE ANALYSISITEM 13.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.10 (15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement on the rough side of single or half brick wall) is derived from 9 priced inputs for 10 sqm and works out to ₹506.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
ANALYSIS OF RATES · ITEM 13.10DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.1724,881.95839.70
0155LABMason (average)day0.8857.00685.60
0115LABCoolieday0.88736.00647.68
0101LABBhistiday0.99816.00807.84
9999MATScaffolding and sundriesL.S.12.612.2728.62
0367MATPortland Cement (OPC-43 grade)tonne0.025,156.00103.12
0155LABMason (average)day0.27857.00231.39
0115LABCoolieday0.27736.00198.72
9999MATScaffolding and sundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
3,560.97
Add 1 % Water charges on “W”
+35.61
TOTAL
3,596.58
Add GST on “X” (multiplying factor 0.2127)
+764.99
TOTAL
4,361.57
Add 15% CPOH on “Y”
+654.24
TOTAL
5,015.81
Add Cess @ 1% on “Z”
+50.16
Cost of 10.00 sqm
5,065.97
Cost of 1.00 sqm
506.60
SAY
₹506.60
D-02/SOURCEPRINTED PAGE 962
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
962

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 962. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.