18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster 1:6 (1 cement : 6 fine sand)

Item number
13.11
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹518.55/ SQM
D-01/RATE ANALYSISITEM 13.11

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.11 (18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster 1:6 (1 cement : 6 fine sand)) is derived from 6 priced inputs for 10 sqm and works out to ₹518.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Under layer Cement mortar 1 : 5 (1 cement
  • : 5 coarse sand)
  • Top layer Cement mortar 1 : 6 (1 cement : 6
  • fine sand)
ANALYSIS OF RATES · ITEM 13.11DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.1443,850.75554.51
SUBRate as per Item Number 3.6 of SH: MortarsRate as per item 3.6cum0.0723,038.50218.77
0155LABMason (average)day1.21857.001,036.97
0115LABCoolieday1.29736.00949.44
0101LABBhistiday1.05816.00856.80
9999MATScaffolding and sundriesL.S.12.612.2728.62
BUILD-UP TO RATE
TOTAL
3,645.11
Add 1 % Water charges on “W”
+36.45
TOTAL
3,681.56
Add GST on “X” (multiplying factor 0.2127)
+783.07
TOTAL
4,464.63
Add 15% CPOH on “Y”
+669.69
TOTAL
5,134.32
Add Cess @ 1% on “Z”
+51.34
Cost of 10.00 sqm
5,185.66
Cost of 1.00 sqm
518.57
SAY
₹518.55
D-02/SOURCEPRINTED PAGE 963
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
963

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 963. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.