Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement

12 mm cement plaster
Item number
13.9.1
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹449.55/ SQM
D-01/RATE ANALYSISITEM 13.9.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.9.1 (Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement 12 mm cement plaster) is derived from 9 priced inputs for 10 sqm and works out to ₹449.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
ANALYSIS OF RATES · ITEM 13.9.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.1444,881.95703.00
0155LABMason (average)day0.67857.00574.19
0115LABCoolieday0.75736.00552.00
0101LABBhistiday0.92816.00750.72
9999MATScaffolding and sundriesL.S.12.612.2728.62
0367MATPortland Cement (OPC-43 grade)tonne0.025,156.00103.12
0155LABMason (average)day0.27857.00231.39
0115LABCoolieday0.27736.00198.72
9999MATScaffolding and sundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
3,160.06
Add 1 % Water charges on “W”
+31.60
TOTAL
3,191.66
Add GST on “X” (multiplying factor 0.2127)
+678.87
TOTAL
3,870.53
Add 15% CPOH on “Y”
+580.58
TOTAL
4,451.11
Add Cess @ 1% on “Z”
+44.51
Cost of 10.00 sqm
4,495.62
Cost of 1.00 sqm
449.56
SAY
₹449.55
D-02/SOURCEPRINTED PAGE 961
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
961

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 961. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.