Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound ) content

With water thinnable cement primer on wall surface having VOC content less than 50 grams/ litre
Item number
13.85.3
Analysis basis
10 sqm
Priced inputs
4
Derived rate
₹73.95/ SQM
D-01/RATE ANALYSISITEM 13.85.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.85.3 (Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound ) content With water thinnable cement primer on wall surface having VOC content less than 50 grams/ litre) is derived from 4 priced inputs for 10 sqm and works out to ₹73.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.85.3DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0808MATWater thinnable cement primer for interior wall surface, having VOC content less than 50 gms/litWater thinnable cement primer for interior wall surface, having VOC content less than 50 grams/ litrelitre0.740.0028.00
9988MATSundries for brushes,sand paper & putty for filling holes including Carriage for primerL.S.8.062.2718.30
0131LABPainterday0.4816.00326.40
0115LABCoolieday0.2736.00147.20
BUILD-UP TO RATE
TOTAL
519.90
Add 1 % Water charges on “W”
+5.20
TOTAL
525.10
Add GST on “X” (multiplying factor 0.2127)
+111.69
TOTAL
636.79
Add 15% CPOH on “Y”
+95.52
TOTAL
732.31
Add Cess @ 1% on “Z”
+7.32
Cost of 10.00 sqm
739.63
Cost of 1.00 sqm
73.96
SAY
₹73.95
D-02/SOURCEPRINTED PAGE 1014
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1014

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1014. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.