CPWD Analysis of Rates · Finishing

Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound ) content

With ready mixed pink or grey primer on wood work (hard and soft wood) having VOC content less than 50 grams/ litre

Item number
13.85.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
6
Derived rate
70.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.85.1 Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound ) content With ready mixed pink or grey primer on wood work (hard and soft wood) having VOC content less than 50 grams/ litre — is derived from 6 priced inputs for 10 sqm and works out to ₹70.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0806Ready mixed pink or grey primer on wood work (hard and soft wood) having VOC content less than 50 gms/litReady mixed pink or grey primer on wood work (hard and soft wood) having VOC content less than 50 grams/ litreMateriallitre0.75100.0075.00
9999PuttyMaterialL.S.2.732.276.20
9977Carriage of materialMaterialL.S.0.392.270.89
0131PainterLabourday0.25816.00204.00
0115CoolieLabourday0.25736.00184.00
9999Sundries for Brushes, sand paper etcMaterialL.S.10.792.2724.49
TOTAL
494.58
Add 1 % Water charges on “W”
4.95
TOTAL
499.53
Add GST on “X” (multiplying factor 0.2127)
106.25
TOTAL
605.78
Add 15% CPOH on “Y”
90.87
TOTAL
696.65
Add Cess @ 1% on “Z”
6.97
Cost of 10.00 sqm
703.62
Cost of 1.00 sqm
70.36
Say
70.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1014. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.