Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 grams/ litre of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour

Two coats
Item number
13.83.2
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹142.80/ SQM
D-01/RATE ANALYSISITEM 13.83.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.83.2 (Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile Organic Compound ) content less than 50 grams/ litre of approved brand and manufacture, including applying additional coats wherever required to achieve even shade and colour Two coats) is derived from 6 priced inputs for 10 sqm and works out to ₹142.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.83.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0804MATPremium acrylic emulsion of interior grade, having VOC content less than 50 gm/ltrPremium plastic acrylic emulsion of interior grade, having VOC content less than 50 grams/ litrelitre0.6210.00126.00
9999MATFor filling holes and cracks with putty etcL.S.5.332.2712.10
9977MATCarriage of materialL.S.1.432.273.25
0131LABPainterday0.54816.00440.64
0115LABCoolieday0.54736.00397.44
9999MATSundries for brushes,sand paper,scaffolding etcL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
1,003.92
Add 1 % Water charges on “W”
+10.04
TOTAL
1,013.96
Add GST on “X” (multiplying factor 0.2127)
+215.67
TOTAL
1,229.63
Add 15% CPOH on “Y”
+184.44
TOTAL
1,414.07
Add Cess @ 1% on “Z”
+14.14
Cost of 10.00 sqm
1,428.21
Cost of 1.00 sqm
142.82
SAY
₹142.80
D-02/SOURCEPRINTED PAGE 1013
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1013

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1013. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.