6 mm plaster on cement concrete or reinforced cement concrete work with white cement based polymer modified self curing mortar of approved make as per the direction of EngineerIn-Charge
- Item number
- 13.86
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹269.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.86 (6 mm plaster on cement concrete or reinforced cement concrete work with white cement based polymer modified self curing mortar of approved make as per the direction of EngineerIn-Charge) is derived from 6 priced inputs for 10 sqm and works out to ₹269.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- i/c 2% wastage
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0772 | MAT | White cement based polymer modified self curing compound in powder form | kg | 46 | 18.00 | 828.00 |
| 9977 | MAT | Carriage of white cement based polymer modified self curing compound in powder form | L.S. | 7.8 | 2.27 | 17.71 |
| 0155 | LAB | Mason (average) | day | 0.51 | 857.00 | 437.07 |
| 0115 | LAB | Coolie | day | 0.75 | 736.00 | 552.00 |
| 9999 | MAT | Extra for removing burrs, cleaning with wire brushes and pock making with pointed tools etc | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | MAT | Scaffolding and sunderies | L.S. | 11.7 | 2.27 | 26.56 |
- TOTAL
- 1,891.74
- Add 1 % Water charges on “W”
- +18.92
- TOTAL
- 1,910.66
- Add GST on “X” (multiplying factor 0.2127)
- +406.40
- TOTAL
- 2,317.06
- Add 15% CPOH on “Y”
- +347.56
- TOTAL
- 2,664.62
- Add Cess @ 1% on “Z”
- +26.65
- Cost of 10 sqm
- 2,691.27
- Cost of 1 sqm
- 269.13
- SAY
- ₹269.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1015
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1015. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.