CPWD Analysis of Rates · Finishing

Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50 grams/ litre, of approved brand and manufacture, including applying additional coats wherever required, to achieve even shade and colour

Two coats

Item number
13.82.2
Analysis basis
Detail of cost for 10 sqm
Priced inputs
6
Derived rate
137.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.82.2 Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50 grams/ litre, of approved brand and manufacture, including applying additional coats wherever required, to achieve even shade and colour Two coats — is derived from 6 priced inputs for 10 sqm and works out to ₹137.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0803Acrylic emulsion , having VOC content less than 50 gm/ltrAcrylic emulsion, having VOC content less than 50 grams/ litreMateriallitre0.84105.0088.20
9999For filling holes and cracks with putty etcMaterialL.S.5.332.2712.10
9977Carriage of materialMaterialL.S.1.432.273.25
0131PainterLabourday0.54816.00440.64
0115CoolieLabourday0.54736.00397.44
9999Sundries for brushes,sand paper,scaffolding etcMaterialL.S.10.792.2724.49
TOTAL
966.12
Add 1 % Water charges on “W”
9.66
TOTAL
975.78
Add GST on “X” (multiplying factor 0.2127)
207.55
TOTAL
1,183.33
Add 15% CPOH on “Y”
177.50
TOTAL
1,360.83
Add Cess @ 1% on “Z”
13.61
Cost of 10.00 sqm
1,374.44
Cost of 1.00 sqm
137.44
Say
137.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1012. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.