CPWD Analysis of Rates · Finishing
Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50 grams/ litre, of approved brand and manufacture, including applying additional coats wherever required, to achieve even shade and colour
One coat
- Item number
- 13.82.1
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹92.00 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.82.1 — Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50 grams/ litre, of approved brand and manufacture, including applying additional coats wherever required, to achieve even shade and colour One coat — is derived from 6 priced inputs for 10 sqm and works out to ₹92.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0803 | Acrylic emulsion , having VOC content less than 50 gm/ltrAcrylic emulsion, having VOC content less than 50 grams/ litreMaterial | litre | 0.53 | 105.00 | 55.65 |
| 9999 | For filling holes and cracks with putty etcMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 9977 | Carriage of materialMaterial | L.S. | 0.91 | 2.27 | 2.07 |
| 0131 | PainterLabour | day | 0.36 | 816.00 | 293.76 |
| 0115 | CoolieLabour | day | 0.36 | 736.00 | 264.96 |
| 9999 | Sundries for brushes,sand paper,scaffolding etcMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 646.84
- Add 1 % Water charges on “W”
- 6.47
- TOTAL
- 653.31
- Add GST on “X” (multiplying factor 0.2127)
- 138.96
- TOTAL
- 792.27
- Add 15% CPOH on “Y”
- 118.84
- TOTAL
- 911.11
- Add Cess @ 1% on “Z”
- 9.11
- Cost of 10.00 sqm
- 920.22
- Cost of 1.00 sqm
- 92.02
- Say
- 92.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1011. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.