CPWD Analysis of Rates · Finishing

Distempering with 1st quality acrylic distemper (ready mixed) having VOC (Volatile Organic Compound ) content less than 50 gram/ litre, of approved brand and manufacturer including applying additional coats wherever required to achieve even shade and colour

Old work (one or more coats)

Item number
13.81.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
62.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.81.1 Distempering with 1st quality acrylic distemper (ready mixed) having VOC (Volatile Organic Compound ) content less than 50 gram/ litre, of approved brand and manufacturer including applying additional coats wherever required to achieve even shade and colour Old work (one or more coats) — is derived from 4 priced inputs for 10 sqm and works out to ₹62.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0802Acrylic distemper 1st quality , having VOC content less than 50 gm/kgAcrylic distemper 1st quality , having VOC content less than 50 grams/ litreMaterialKg0.6245.0027.90
9988Sundries for brushes,sand paper,scaffolding including Carriage for distemperMaterialL.S.8.062.2718.30
0131PainterLabourday0.33816.00269.28
0115CoolieLabourday0.17736.00125.12
TOTAL
440.60
Add 1 % Water charges on “W”
4.41
TOTAL
445.01
Add GST on “X” (multiplying factor 0.2127)
94.65
TOTAL
539.66
Add 15% CPOH on “Y”
80.95
TOTAL
620.61
Add Cess @ 1% on “Z”
6.21
Cost of 10.00 sqm
626.82
Cost of 1.00 sqm
62.68
Say
62.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1011. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.