Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete
- Item number
- 13.80
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹156.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.80 (Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete) is derived from 5 priced inputs for 10 sqm and works out to ₹156.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 10x0.001x1429 = 14.29kg
- Total = 14.58kg Say 14.58 kg
- Add 2% wastage= 0.29kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0824 | MAT | Cement base wall care puttyWhite cement based putty | kg | 14.58 | 18.00 | 262.44 |
| 9977 | MAT | Carriage | L.S. | 3.9 | 2.27 | 8.85 |
| 0122 | LAB | Mason (for plaster of paris work) 1st class | day | 0.45 | 897.00 | 403.65 |
| 0114 | LAB | Beldar | day | 0.45 | 736.00 | 331.20 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 40 | 2.27 | 90.80 |
- TOTAL
- 1,096.94
- Add 1 % Water charges on “W”
- +10.97
- TOTAL
- 1,107.91
- Add GST on “X” (multiplying factor 0.2127)
- +235.65
- TOTAL
- 1,343.56
- Add 15% CPOH on “Y”
- +201.53
- TOTAL
- 1,545.09
- Add Cess @ 1% on “Z”
- +15.45
- Cost of 10.00 sqm
- 1,560.54
- Cost of 1.00 sqm
- 156.05
- SAY
- ₹156.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1010
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1010. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.