Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete

Item number
13.80
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹156.05/ SQM
D-01/RATE ANALYSISITEM 13.80

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.80 (Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete) is derived from 5 priced inputs for 10 sqm and works out to ₹156.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10x0.001x1429 = 14.29kg
  • Total = 14.58kg Say 14.58 kg
  • Add 2% wastage= 0.29kg
ANALYSIS OF RATES · ITEM 13.80DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0824MATCement base wall care puttyWhite cement based puttykg14.5818.00262.44
9977MATCarriageL.S.3.92.278.85
0122LABMason (for plaster of paris work) 1st classday0.45897.00403.65
0114LABBeldarday0.45736.00331.20
9999MATScaffolding and sundriesL.S.402.2790.80
BUILD-UP TO RATE
TOTAL
1,096.94
Add 1 % Water charges on “W”
+10.97
TOTAL
1,107.91
Add GST on “X” (multiplying factor 0.2127)
+235.65
TOTAL
1,343.56
Add 15% CPOH on “Y”
+201.53
TOTAL
1,545.09
Add Cess @ 1% on “Z”
+15.45
Cost of 10.00 sqm
1,560.54
Cost of 1.00 sqm
156.05
SAY
₹156.05
D-02/SOURCEPRINTED PAGE 1010
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1010

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1010. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.