Skip to main content

CPWD Analysis of Rates · Finishing

Extra for washed stone grit plaster on circular work not exceeding 6 m in radius (in two coats)

Item number
13.75
Analysis basis
Detail of cost for 10 sqm
Priced inputs
3
Derived rate
133.55 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.75 Extra for washed stone grit plaster on circular work not exceeding 6 m in radius (in two coats) — is derived from 3 priced inputs for 10 sqm and works out to ₹133.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
0114BeldarLabourday0.5736.00368.00
9999SundriesMaterialL.S.53.822.27122.17
TOTAL
938.67
Add 1 % Water charges on “W”
9.39
TOTAL
948.06
Add GST on “X” (multiplying factor 0.2127)
201.65
TOTAL
1,149.71
Add 15% CPOH on “Y”
172.46
TOTAL
1,322.17
Add Cess @ 1% on “Z”
13.22
Cost of 10.00 sqm
1,335.39
Cost of 1.00 sqm
133.54
Say
133.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1008. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works