Extra for washed stone grit plaster on circular work not exceeding 6 m in radius (in two coats)
- Item number
- 13.75
- Analysis basis
- 10 sqm
- Priced inputs
- 3
- Derived rate
- ₹133.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.75 (Extra for washed stone grit plaster on circular work not exceeding 6 m in radius (in two coats)) is derived from 3 priced inputs for 10 sqm and works out to ₹133.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 938.67
- Add 1 % Water charges on “W”
- +9.39
- TOTAL
- 948.06
- Add GST on “X” (multiplying factor 0.2127)
- +201.65
- TOTAL
- 1,149.71
- Add 15% CPOH on “Y”
- +172.46
- TOTAL
- 1,322.17
- Add Cess @ 1% on “Z”
- +13.22
- Cost of 10.00 sqm
- 1,335.39
- Cost of 1.00 sqm
- 133.54
- SAY
- ₹133.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1008
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1008. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate