CPWD Analysis of Rates · Finishing

Forming groove of uniform size from 12x12 mm and upto 25x15 mm in the top layer of washed stone grit plastered surface as per approved pattern, including providing and fixing aluminum channels of appropriate size and thickness (not less than 2 mm), nailed to the under layer with rust proof screws and nails and finishing the groove complete as per specifications and direction of the Engineer-in-Charge

Item number
13.76
Analysis basis
Detail of cost for 30 metre
Priced inputs
6
Derived rate
100.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.76 Forming groove of uniform size from 12x12 mm and upto 25x15 mm in the top layer of washed stone grit plastered surface as per approved pattern, including providing and fixing aluminum channels of appropriate size and thickness (not less than 2 mm), nailed to the under layer with rust proof screws and nails and finishing the groove complete as per specifications and direction of the Engineer-in-Charge — is derived from 6 priced inputs for 30 metre and works out to ₹100.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Aluminium channel section 15 x 15 x 2 mm
  • (weight 0.221 kg/mtr)
  • Qty = 30 + 5% wastage = 31.5 m @ 0.221
  • kg/m = 6.96 kg.
  • Labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
7306Aluminium T or L sectionsMaterialkilogram6.96198.001,378.08
9977CarriageMaterialL.S.38.982.2788.48
0117Assistant Fitter or 2nd class FitterLabourday0.46816.00375.36
0114BeldarLabourday0.15736.00110.40
9999SundriesMaterialL.S.2.862.276.49
9999Nails and cement mortarMaterialL.S.71.762.27162.90
TOTAL
2,121.71
Add 1 % Water charges on “W”
21.22
TOTAL
2,142.93
Add GST on “X” (multiplying factor 0.2127)
455.80
TOTAL
2,598.73
Add 15% CPOH on “Y”
389.81
TOTAL
2,988.54
Add Cess @ 1% on “Z”
29.89
Cost of 30.00 metre
3,018.43
Cost of 1.00 metre
100.61
Say
100.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1008. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.