Extra for washed grit plaster on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part thereof
- Item number
- 13.74
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹165.85/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.74 (Extra for washed grit plaster on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part thereof) is derived from 5 priced inputs for 10 sqm and works out to ₹165.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Scaffolding | L.S. | 215.28 | 2.27 | 488.69 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.3 | 897.00 | 269.10 |
| 0114 | LAB | Beldar | day | 0.3 | 736.00 | 220.80 |
| 0101 | LAB | Bhisti | day | 0.15 | 816.00 | 122.40 |
| 9999 | MAT | Sundries | L.S. | 28.6 | 2.27 | 64.92 |
- TOTAL
- 1,165.91
- Add 1 % Water charges on “W”
- +11.66
- TOTAL
- 1,177.57
- Add GST on “X” (multiplying factor 0.2127)
- +250.47
- TOTAL
- 1,428.04
- Add 15% CPOH on “Y”
- +214.21
- TOTAL
- 1,642.25
- Add Cess @ 1% on “Z”
- +16.42
- Cost of 10.00 sqm
- 1,658.67
- Cost of 1.00 sqm
- 165.87
- SAY
- ₹165.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1008
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1008. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.