Forming groove of uniform size in the top layer of washed stone grit plaster as per approved pattern using wooden battens, nailed to the under layer, including removal of wooden battens, repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge
- Item number
- 13.73.1
- Analysis basis
- 30 mtrs
- Priced inputs
- 8
- Derived rate
- ₹75.15/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.73.1 (Forming groove of uniform size in the top layer of washed stone grit plaster as per approved pattern using wooden battens, nailed to the under layer, including removal of wooden battens, repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge : 15 mm wide and 15 mm deep groove) is derived from 8 priced inputs for 30 mtrs and works out to ₹75.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Second class kail wood in plank 30 x0.015
- x0.015m =6.75cudm
- Wastage @ 10% = 0.68
- Total = 7.43 cudm
- Assuming that the battens shall become
- unserviceable after using 5 times
- Labour for making battens
- Labour for nailing the battens to under layer
- and finishing and repairing grooves
- Cost for using once = 7.43 / 5 = 1.48 cudm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1198 | MAT | Second class kail wood in planks | 10 cudm | 0.148 | 260.00 | 38.48 |
| 9977 | MAT | Carriage of wood | L.S. | 0.39 | 2.27 | 0.89 |
| 0112 | LAB | Carpenter 2nd class | day | 0.15 | 816.00 | 122.40 |
| 0114 | LAB | Beldar | day | 0.15 | 736.00 | 110.40 |
| 9999 | MAT | Sundries | L.S. | 2.86 | 2.27 | 6.49 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.7 | 897.00 | 627.90 |
| 0114 | LAB | Beldar | day | 0.7 | 736.00 | 515.20 |
| 9999 | MAT | Nails and cement mortar | L.S. | 71.76 | 2.27 | 162.90 |
- TOTAL
- 1,584.66
- Add 1 % Water charges on “W”
- +15.85
- TOTAL
- 1,600.51
- Add GST on “X” (multiplying factor 0.2127)
- +340.43
- TOTAL
- 1,940.94
- Add 15% CPOH on “Y”
- +291.14
- TOTAL
- 2,232.08
- Add Cess @ 1% on “Z”
- +22.32
- Cost of 30.00 mtrs
- 2,254.40
- Cost of 1.00 metre
- 75.15
- SAY
- ₹75.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1006
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1006. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.