CPWD Analysis of Rates · Finishing
Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately)
- Item number
- 13.72
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 21
- Derived rate
- ₹1,162.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.72 — Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately) — is derived from 21 priced inputs for 10 sqm and works out to ₹1,162.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 12 mm cement plaster with
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Applying cement slurry
- Top layer 15 mm thick stone chipping plaster Quantity required = 0.172 cum including
- wastage
- Preparation of cement concrete mix 1:1/2:2
- (1 cement : 1/2 coarse sand : 2 stone chipping 10 mm nominal size)
- Labour for washing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.144 | 4,211.70 | 606.48 | |
| 0155 | Mason (average)Labour | day | 0.67 | 857.00 | 574.19 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 0101 | BhistiLabour | day | 0.92 | 816.00 | 750.72 |
| 9999 | ScaffoldingMaterial | L.S. | 8.97 | 2.27 | 20.36 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.02 | 5,156.00 | 103.12 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 2911 | Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterial | cum | 0.14 | 1,400.00 | 196.00 |
| 0982 | Coarse sand (zone III)Material | cum | 0.04 | 1,450.00 | 58.00 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.1 | 5,156.00 | 515.60 |
| 0114 | BeldarLabour | day | 0.1 | 736.00 | 73.60 |
| 0101 | BhistiLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Hire and running charges of mechanical mixerMaterial | L.S. | 4.29 | 2.27 | 9.74 |
| 9999 | SundriesMaterial | L.S. | 2.08 | 2.27 | 4.72 |
| 0123 | Mason 1st classMason 1st classLabour | Day | 1.75 | 897.00 | 1,569.75 |
| 0114 | BeldarLabour | Day | 1.75 | 736.00 | 1,288.00 |
| 0101 | BhistiLabour | Day | 0.3 | 816.00 | 244.80 |
| 9999 | ScaffoldingMaterial | L.S. | 24.44 | 2.27 | 55.48 |
| 0123 | Mason 1st classMason 1st classLabour | Day | 1 | 897.00 | 897.00 |
| 0115 | CoolieLabour | Day | 0.5 | 736.00 | 368.00 |
| 9999 | Sundries soft brushes etcMaterial | L.S. | 25.22 | 2.27 | 57.25 |
- TOTAL
- 8,169.61
- Add 1 % Water charges on “W”
- 81.70
- TOTAL
- 8,251.31
- Add GST on “X” (multiplying factor 0.2127)
- 1,755.05
- TOTAL
- 10,006.36
- Add 15% CPOH on “Y”
- 1,500.95
- TOTAL
- 11,507.31
- Add Cess @ 1% on “Z”
- 115.07
- Cost of 10.00 sqm
- 11,622.38
- Cost of 1.00 sqm
- 1,162.24
- Say
- 1,162.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1005. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.