Skip to main content
R/DAR 2023

Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately)

Item number
13.72
Analysis basis
10 sqm
Priced inputs
21
Derived rate
₹1,162.25/ SQM
D-01/RATE ANALYSISITEM 13.72

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.72 (Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately)) is derived from 21 priced inputs for 10 sqm and works out to ₹1,162.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Under layer 12 mm cement plaster with
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Applying cement slurry
  • Top layer 15 mm thick stone chipping plaster Quantity required = 0.172 cum including
  • wastage
  • Preparation of cement concrete mix 1:1/2:2
  • (1 cement : 1/2 coarse sand : 2 stone chipping 10 mm nominal size)
  • Labour for washing
ANALYSIS OF RATES · ITEM 13.72DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.1444,211.70606.48
0155LABMason (average)day0.67857.00574.19
0114LABBeldarday0.75736.00552.00
0101LABBhistiday0.92816.00750.72
9999MATScaffoldingL.S.8.972.2720.36
0367MATPortland Cement (OPC-43 grade)tonne0.025,156.00103.12
0114LABBeldarday0.25736.00184.00
2911MATStone chippings/ screenings 10/ 11.2 mm nominal sizecum0.141,400.00196.00
0982MATCoarse sand (zone III)cum0.041,450.0058.00
0367MATPortland Cement (OPC-43 grade)tonne0.15,156.00515.60
0114LABBeldarday0.1736.0073.60
0101LABBhistiday0.05816.0040.80
9999MATHire and running charges of mechanical mixerL.S.4.292.279.74
9999MATSundriesL.S.2.082.274.72
0123LABMason 1st classMason 1st classDay1.75897.001,569.75
0114LABBeldarDay1.75736.001,288.00
0101LABBhistiDay0.3816.00244.80
9999MATScaffoldingL.S.24.442.2755.48
0123LABMason 1st classMason 1st classDay1897.00897.00
0115LABCoolieDay0.5736.00368.00
9999MATSundries soft brushes etcL.S.25.222.2757.25
BUILD-UP TO RATE
TOTAL
8,169.61
Add 1 % Water charges on “W”
+81.70
TOTAL
8,251.31
Add GST on “X” (multiplying factor 0.2127)
+1,755.05
TOTAL
10,006.36
Add 15% CPOH on “Y”
+1,500.95
TOTAL
11,507.31
Add Cess @ 1% on “Z”
+115.07
Cost of 10.00 sqm
11,622.38
Cost of 1.00 sqm
1,162.24
SAY
₹1,162.25
D-02/SOURCEPRINTED PAGE 1005
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1005

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1005. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.