Varnishing with varnish of approved brand and manufacture

Two or more coats of glue sizing with copal varnish over an under coat of flatting varnish
Item number
13.67.1
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹236.10/ SQM
D-01/RATE ANALYSISITEM 13.67.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.67.1 (Varnishing with varnish of approved brand and manufacture : Two or more coats of glue sizing with copal varnish over an under coat of flatting varnish) is derived from 9 priced inputs for 10 sqm and works out to ₹236.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (0.36+0.54=0.90)
  • (0.36+0.54=0.90)
ANALYSIS OF RATES · ITEM 13.67.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0856MATOrdinary varnishlitre0.7110.0077.00
0763MATGluekilogram0.0780.005.60
0857MATSuperior copal varnishlitre1.16115.00133.40
9977MATCarriageL.S.1.432.273.25
9999MATPutty for repair to holes etcL.S.5.332.2712.10
0131LABPainterday0.9816.00734.40
0115LABCoolieday0.9736.00662.40
9999MATBrushes, sand paper etcL.S.6.762.2715.35
9999MATSundriesL.S.7.152.2716.23
BUILD-UP TO RATE
TOTAL
1,659.73
Add 1 % Water charges on “W”
+16.60
TOTAL
1,676.33
Add GST on “X” (multiplying factor 0.2127)
+356.56
TOTAL
2,032.89
Add 15% CPOH on “Y”
+304.93
TOTAL
2,337.82
Add Cess @ 1% on “Z”
+23.38
Cost of 10.00 sqm
2,361.20
Cost of 1.00 sqm
236.12
SAY
₹236.10
D-02/SOURCEPRINTED PAGE 1002
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1002

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1002. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.