Varnishing with varnish of approved brand and manufacture
- Item number
- 13.67.1
- Analysis basis
- 10 sqm
- Priced inputs
- 9
- Derived rate
- ₹236.10/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.67.1 (Varnishing with varnish of approved brand and manufacture : Two or more coats of glue sizing with copal varnish over an under coat of flatting varnish) is derived from 9 priced inputs for 10 sqm and works out to ₹236.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- (0.36+0.54=0.90)
- (0.36+0.54=0.90)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0856 | MAT | Ordinary varnish | litre | 0.7 | 110.00 | 77.00 |
| 0763 | MAT | Glue | kilogram | 0.07 | 80.00 | 5.60 |
| 0857 | MAT | Superior copal varnish | litre | 1.16 | 115.00 | 133.40 |
| 9977 | MAT | Carriage | L.S. | 1.43 | 2.27 | 3.25 |
| 9999 | MAT | Putty for repair to holes etc | L.S. | 5.33 | 2.27 | 12.10 |
| 0131 | LAB | Painter | day | 0.9 | 816.00 | 734.40 |
| 0115 | LAB | Coolie | day | 0.9 | 736.00 | 662.40 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 6.76 | 2.27 | 15.35 |
| 9999 | MAT | Sundries | L.S. | 7.15 | 2.27 | 16.23 |
- TOTAL
- 1,659.73
- Add 1 % Water charges on “W”
- +16.60
- TOTAL
- 1,676.33
- Add GST on “X” (multiplying factor 0.2127)
- +356.56
- TOTAL
- 2,032.89
- Add 15% CPOH on “Y”
- +304.93
- TOTAL
- 2,337.82
- Add Cess @ 1% on “Z”
- +23.38
- Cost of 10.00 sqm
- 2,361.20
- Cost of 1.00 sqm
- 236.12
- SAY
- ₹236.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1002
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1002. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.