Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to give an even shade
- Item number
- 13.65.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹140.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.65.1 (Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to give an even shade : Two or more coats on new work) is derived from 6 priced inputs for 10 sqm and works out to ₹140.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0828 | MAT | Anticorrosive bituminous paint (black) | litre | 0.95 | 120.00 | 114.00 |
| 9977 | MAT | Carriage | L.S. | 1.43 | 2.27 | 3.25 |
| 0131 | LAB | Painter | day | 0.54 | 816.00 | 440.64 |
| 0115 | LAB | Coolie | day | 0.54 | 736.00 | 397.44 |
| 9999 | MAT | Putty, brushes, sand paper etc | L.S. | 5.33 | 2.27 | 12.10 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 985.73
- Add 1 % Water charges on “W”
- +9.86
- TOTAL
- 995.59
- Add GST on “X” (multiplying factor 0.2127)
- +211.76
- TOTAL
- 1,207.35
- Add 15% CPOH on “Y”
- +181.10
- TOTAL
- 1,388.45
- Add Cess @ 1% on “Z”
- +13.88
- Cost of 10.00 sqm
- 1,402.33
- Cost of 1.00 sqm
- 140.23
- SAY
- ₹140.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1001
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1001. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.