Skip to main content
R/DAR 2023

Painting with acid proof paint of approved brand and manufacture of required colour to give an even shade

Two or more coats on new work
Item number
13.64.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹163.35/ SQM
D-01/RATE ANALYSISITEM 13.64.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.64.1 (Painting with acid proof paint of approved brand and manufacture of required colour to give an even shade : Two or more coats on new work) is derived from 7 priced inputs for 10 sqm and works out to ₹163.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.64.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0827MATAcid proof paint (chocolate or black)litre1.16225.00261.00
9977MATCarriage of paintL.S.1.432.273.25
9999MATPutty etcL.S.5.332.2712.10
0131LABPainterday0.54816.00440.64
0115LABCoolieday0.54736.00397.44
9999MATBrushes, sand paper etcL.S.6.762.2715.35
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
1,148.08
Add 1 % Water charges on “W”
+11.48
TOTAL
1,159.56
Add GST on “X” (multiplying factor 0.2127)
+246.64
TOTAL
1,406.20
Add 15% CPOH on “Y”
+210.93
TOTAL
1,617.13
Add Cess @ 1% on “Z”
+16.17
Cost of 10.00 sqm
1,633.30
Cost of 1.00 sqm
163.33
SAY
₹163.35
D-02/SOURCEPRINTED PAGE 1001
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1001

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1001. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.