Skip to main content

CPWD Analysis of Rates · Finishing

Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s specifications including appropriate priming coat, preparation of surface, etc. complete

On concrete work

Item number
13.52.2
Analysis basis
Detail of cost for 10 sqm
Priced inputs
14
Derived rate
235.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.52.2 Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s specifications including appropriate priming coat, preparation of surface, etc. complete On concrete work — is derived from 14 priced inputs for 10 sqm and works out to ₹235.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • PRIMING COAT
  • EPOXY PAINTING
CodeInputUnitQuantityRate (INR)Amount (INR)
0808Water thinnable cement primer for interior wall surface, having VOC content less than 50 grams/ litreMateriallitre0.8440.0033.60
9999PuttyMaterialL.S.13.522.2730.69
9977CarriageMaterialL.S.0.522.271.18
0131PainterLabourday0.25816.00204.00
0115CoolieLabourday0.25736.00184.00
9999Brushes, sand paper etcMaterialL.S.2.732.276.20
9999SundriesMaterialL.S.8.062.2718.30
7239Epoxy paintMateriallitre1.21230.00278.30
9999Materials for filling in holes and cracksMaterialL.S.6.762.2715.35
9977Carriage of materialMaterialL.S.1.432.273.25
0131PainterLabourday0.54816.00440.64
0115CoolieLabourday0.54736.00397.44
9999Putty, brushes, sand paper etcMaterialL.S.10.792.2724.49
9999SundriesMaterialL.S.6.762.2715.35
TOTAL
1,652.79
Add 1 % Water charges on “W”
16.53
TOTAL
1,669.32
Add GST on “X” (multiplying factor 0.2127)
355.06
TOTAL
2,024.38
Add 15% CPOH on “Y”
303.66
TOTAL
2,328.04
Add Cess @ 1% on “Z”
23.28
Cost of 10.00 sqm
2,351.32
Cost of 1.00 sqm
235.13
Say
235.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 993. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works