CPWD Analysis of Rates · Finishing

Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s specifications including appropriate priming coat, preparation of surface, etc. complete

On steel work

Item number
13.52.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
13
Derived rate
241.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.52.1 Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s specifications including appropriate priming coat, preparation of surface, etc. complete On steel work — is derived from 13 priced inputs for 10 sqm and works out to ₹241.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • PRIMING COAT
  • EPOXY PAINTING
CodeInputUnitQuantityRate (INR)Amount (INR)
4202Red oxide Zinc chromate primerMateriallitre0.75140.00105.00
9999PuttyMaterialL.S.2.732.276.20
9977CarriageMaterialL.S.0.392.270.89
0131PainterLabourday0.25816.00204.00
0115CoolieLabourday0.25736.00184.00
9999Brushes, sand paper etcMaterialL.S.5.462.2712.39
9999SundriesMaterialL.S.10.662.2724.20
7239Epoxy paintMateriallitre1.25230.00287.50
9977Carriage of materialMaterialL.S.1.432.273.25
0131PainterLabourday0.54816.00440.64
0115CoolieLabourday0.54736.00397.44
9999Putty, brushes, sand paper etcMaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.8.062.2718.30
TOTAL
1,699.16
Add 1 % Water charges on “W”
16.99
TOTAL
1,716.15
Add GST on “X” (multiplying factor 0.2127)
365.03
TOTAL
2,081.18
Add 15% CPOH on “Y”
312.18
TOTAL
2,393.36
Add Cess @ 1% on “Z”
23.93
Cost of 10.00 sqm
2,417.29
Cost of 1.00 sqm
241.73
Say
241.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 992. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.