R/DAR 2023

Applying priming coat

With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works
Item number
13.50.3
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹67.40/ SQM
D-01/RATE ANALYSISITEM 13.50.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.50.3 (Applying priming coat: With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works) is derived from 5 priced inputs for 10 sqm and works out to ₹67.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.50.3DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
4202MATRed oxide Zinc chromate primerlitre0.54140.0075.60
9977MATCarriageL.S.0.522.271.18
0131LABPainterday0.24816.00195.84
0115LABCoolieday0.24736.00176.64
9999MATBrushes,sand paper including sundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
473.75
Add 1 % Water charges on “W”
+4.74
TOTAL
478.49
Add GST on “X” (multiplying factor 0.2127)
+101.77
TOTAL
580.26
Add 15% CPOH on “Y”
+87.04
TOTAL
667.30
Add Cess @ 1% on “Z”
+6.67
Cost of 10.00 sqm
673.97
Cost of 1.00 sqm
67.40
SAY
₹67.40
D-02/SOURCEPRINTED PAGE 990
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
990

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 990. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.