CPWD Analysis of Rates · Finishing
Finishing walls with ready mixed Premium acrylic emulsion paint (Company Depot Tinted) having VOC less than 50 gm/litre and UV resistance as per IS 15489:2004, Alkali & fungal resistance, dirt resistance exterior paint of required shade with silicon additives
New work (Two or more coats applied @ 1.43 litre/ 10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm
- Item number
- 13.48A.1
- Analysis basis
- Details of cost for 10 sqm (Based on item
- Priced inputs
- 7
- Derived rate
- ₹181.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.48A.1 — Finishing walls with ready mixed Premium acrylic emulsion paint (Company Depot Tinted) having VOC less than 50 gm/litre and UV resistance as per IS 15489:2004, Alkali & fungal resistance, dirt resistance exterior paint of required shade with silicon additives New work (Two or more coats applied @ 1.43 litre/ 10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm — is derived from 7 priced inputs for 10 sqm and works out to ₹181.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- no 13.47)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0836 | 100% Premium acrylic dirt resistance, Silicone additives exterior paintMaterial | litre | 1.43 | 300.00 | 429.00 |
| 0837 | Acrylic Exterior PrimerMaterial | litre | 0.9 | 80.00 | 72.00 |
| 9977 | Carriage of materialMaterial | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | PainterLabour | day | 0.6 | 816.00 | 489.60 |
| 0115 | CoolieLabour | day | 0.3 | 736.00 | 220.80 |
| 0101 | BhistiLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Sundries for brushes,sand paper & putty for filling holes etcMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,274.04
- Add 1 % Water charges on “W”
- 12.74
- TOTAL
- 1,286.78
- Add GST on “X” (multiplying factor 0.2127)
- 273.70
- TOTAL
- 1,560.48
- Add 15% CPOH on “Y”
- 234.07
- TOTAL
- 1,794.55
- Add Cess @ 1% on “Z”
- 17.95
- Cost of 10 sqm
- 1,812.50
- Cost of 1 sqm
- 181.25
- Say
- 181.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 989. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.