Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications
- Item number
- 13.48.3
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹170.70/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.48.3 (Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/10 sqm of approved brand and manufacture) is derived from 8 priced inputs for 10 sqm and works out to ₹170.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8504 | MAT | Multi surface paint | litre | 0.9 | 350.00 | 315.00 |
| 8510 | MAT | Metal Primer (U.G.) | litre | 0.8 | 120.00 | 96.00 |
| 9977 | MAT | Carriage of material | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | LAB | Painter | day | 0.6 | 816.00 | 489.60 |
| 0115 | LAB | Coolie | day | 0.3 | 736.00 | 220.80 |
| 0101 | LAB | Bhisti | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 7.02 | 2.27 | 15.94 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,199.98
- Add 1 % Water charges on “W”
- +12.00
- TOTAL
- 1,211.98
- Add GST on “X” (multiplying factor 0.2127)
- +257.79
- TOTAL
- 1,469.77
- Add 15% CPOH on “Y”
- +220.47
- TOTAL
- 1,690.24
- Add Cess @ 1% on “Z”
- +16.90
- Cost of 10.00 sqm
- 1,707.14
- Cost of 1.00 sqm
- 170.71
- SAY
- ₹170.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 989
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 989. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.