Skip to main content
R/DAR 2023

Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications

Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10 sqm of approved brand and manufacture
Item number
13.48.2
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹176.25/ SQM
D-01/RATE ANALYSISITEM 13.48.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.48.2 (Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10 sqm of approved brand and manufacture) is derived from 8 priced inputs for 10 sqm and works out to ₹176.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.48.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8504MATMulti surface paintlitre0.9350.00315.00
8509MATSpecial Primer (C.W.)litre0.75180.00135.00
9977MATCarriage of materialL.S.1.562.273.54
0131LABPainterday0.6816.00489.60
0115LABCoolieday0.3736.00220.80
0101LABBhistiday0.05816.0040.80
9999MATBrushes, sand paper etcL.S.7.022.2715.94
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
1,238.98
Add 1 % Water charges on “W”
+12.39
TOTAL
1,251.37
Add GST on “X” (multiplying factor 0.2127)
+266.17
TOTAL
1,517.54
Add 15% CPOH on “Y”
+227.63
TOTAL
1,745.17
Add Cess @ 1% on “Z”
+17.45
Cost of 10.00 sqm
1,762.62
Cost of 1.00 sqm
176.26
SAY
₹176.25
D-02/SOURCEPRINTED PAGE 988
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
988

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 988. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.