Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications
- Item number
- 13.48.2
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹176.25/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.48.2 (Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10 sqm of approved brand and manufacture) is derived from 8 priced inputs for 10 sqm and works out to ₹176.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8504 | MAT | Multi surface paint | litre | 0.9 | 350.00 | 315.00 |
| 8509 | MAT | Special Primer (C.W.) | litre | 0.75 | 180.00 | 135.00 |
| 9977 | MAT | Carriage of material | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | LAB | Painter | day | 0.6 | 816.00 | 489.60 |
| 0115 | LAB | Coolie | day | 0.3 | 736.00 | 220.80 |
| 0101 | LAB | Bhisti | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 7.02 | 2.27 | 15.94 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,238.98
- Add 1 % Water charges on “W”
- +12.39
- TOTAL
- 1,251.37
- Add GST on “X” (multiplying factor 0.2127)
- +266.17
- TOTAL
- 1,517.54
- Add 15% CPOH on “Y”
- +227.63
- TOTAL
- 1,745.17
- Add Cess @ 1% on “Z”
- +17.45
- Cost of 10.00 sqm
- 1,762.62
- Cost of 1.00 sqm
- 176.26
- SAY
- ₹176.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 988
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 988. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.