CPWD Analysis of Rates · Finishing
Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications
Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10 sqm of approved brand and manufacture
- Item number
- 13.48.2
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹176.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.48.2 — Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications : Painting wood work with Deluxe Multi Surface Paint of required shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10 sqm of approved brand and manufacture — is derived from 8 priced inputs for 10 sqm and works out to ₹176.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8504 | Multi surface paintMaterial | litre | 0.9 | 350.00 | 315.00 |
| 8509 | Special Primer (C.W.)Material | litre | 0.75 | 180.00 | 135.00 |
| 9977 | Carriage of materialMaterial | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | PainterLabour | day | 0.6 | 816.00 | 489.60 |
| 0115 | CoolieLabour | day | 0.3 | 736.00 | 220.80 |
| 0101 | BhistiLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Brushes, sand paper etcMaterial | L.S. | 7.02 | 2.27 | 15.94 |
| 9999 | SundriesMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,238.98
- Add 1 % Water charges on “W”
- 12.39
- TOTAL
- 1,251.37
- Add GST on “X” (multiplying factor 0.2127)
- 266.17
- TOTAL
- 1,517.54
- Add 15% CPOH on “Y”
- 227.63
- TOTAL
- 1,745.17
- Add Cess @ 1% on “Z”
- 17.45
- Cost of 10.00 sqm
- 1,762.62
- Cost of 1.00 sqm
- 176.26
- Say
- 176.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 988. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.