Finishing walls with Acrylic Smooth exterior paint of required shade
- Item number
- 13.46.1
- Analysis basis
- 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹160.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.46.1 (Finishing walls with Acrylic Smooth exterior paint of required shade : New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)) is derived from 7 priced inputs for 10 sqm and works out to ₹160.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8505 | MAT | Acrylic exterior paint | litre | 1.67 | 170.00 | 283.90 |
| 0837 | MAT | Acrylic Exterior Primer | litre | 0.9 | 80.00 | 72.00 |
| 9977 | MAT | Carriage of material | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | LAB | Painter | day | 0.6 | 816.00 | 489.60 |
| 0115 | LAB | Coolie | day | 0.3 | 736.00 | 220.80 |
| 0101 | LAB | Bhisti | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Sundries for brushes,sand paper & putty for filling holes etc | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,128.94
- Add 1 % Water charges on “W”
- +11.29
- TOTAL
- 1,140.23
- Add GST on “X” (multiplying factor 0.2127)
- +242.53
- TOTAL
- 1,382.76
- Add 15% CPOH on “Y”
- +207.41
- TOTAL
- 1,590.17
- Add Cess @ 1% on “Z”
- +15.90
- Cost of 10.00 sqm
- 1,606.07
- Cost of 1.00 sqm
- 160.61
- SAY
- ₹160.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 987
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 987. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.