CPWD Analysis of Rates · Finishing
Finishing walls with textured exterior paint of required shade
New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/10 sqm
- Item number
- 13.45.1
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹223.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.45.1 — Finishing walls with textured exterior paint of required shade : New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/10 sqm — is derived from 8 priced inputs for 10 sqm and works out to ₹223.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8507 | Textured exterior paintMaterial | litre | 3.28 | 185.00 | 606.80 |
| 0837 | Acrylic Exterior PrimerMaterial | kilogram | 2.2 | 80.00 | 176.00 |
| 9977 | Carriage of materialMaterial | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | PainterLabour | day | 0.6 | 816.00 | 489.60 |
| 0115 | CoolieLabour | day | 0.3 | 736.00 | 220.80 |
| 0101 | BhistiLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Brushes, sand paper etcMaterial | L.S. | 7.02 | 2.27 | 15.94 |
| 9999 | SundriesMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,571.78
- Add 1 % Water charges on “W”
- 15.72
- TOTAL
- 1,587.50
- Add GST on “X” (multiplying factor 0.2127)
- 337.66
- TOTAL
- 1,925.16
- Add 15% CPOH on “Y”
- 288.77
- TOTAL
- 2,213.93
- Add Cess @ 1% on “Z”
- 22.14
- Cost of 10.00 sqm
- 2,236.07
- Cost of 1.00 sqm
- 223.61
- Say
- 223.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 986. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works