Finishing walls with textured exterior paint of required shade

New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/10 sqm
Item number
13.45.1
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹223.60/ SQM
D-01/RATE ANALYSISITEM 13.45.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.45.1 (Finishing walls with textured exterior paint of required shade : New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/10 sqm) is derived from 8 priced inputs for 10 sqm and works out to ₹223.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.45.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8507MATTextured exterior paintlitre3.28185.00606.80
0837MATAcrylic Exterior Primerkilogram2.280.00176.00
9977MATCarriage of materialL.S.1.562.273.54
0131LABPainterday0.6816.00489.60
0115LABCoolieday0.3736.00220.80
0101LABBhistiday0.05816.0040.80
9999MATBrushes, sand paper etcL.S.7.022.2715.94
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
1,571.78
Add 1 % Water charges on “W”
+15.72
TOTAL
1,587.50
Add GST on “X” (multiplying factor 0.2127)
+337.66
TOTAL
1,925.16
Add 15% CPOH on “Y”
+288.77
TOTAL
2,213.93
Add Cess @ 1% on “Z”
+22.14
Cost of 10.00 sqm
2,236.07
Cost of 1.00 sqm
223.61
SAY
₹223.60
D-02/SOURCEPRINTED PAGE 986
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
986

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 986. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.