New work (Two or more coats applied @ 3.84 kg/10 sqm)
Item number
13.44.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹116.90/ SQM
D-01/RATE ANALYSISITEM 13.44.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.44.1 (Finishing walls with water proofing cement paint of required shade : New work (Two or more coats applied @ 3.84 kg/10 sqm)) is derived from 7 priced inputs for 10 sqm and works out to ₹116.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.44.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0851MATWater proofing cement paintkilogram3.8441.00157.44
9977MATCarriage of materialL.S.1.562.273.54
0131LABPainterday0.46816.00375.36
0115LABCoolieday0.23736.00169.28
0101LABBhistiday0.1816.0081.60
9999MATBrushes, sand paper etcL.S.7.152.2716.23
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
821.75
Add 1 % Water charges on “W”
+8.22
TOTAL
829.97
Add GST on “X” (multiplying factor 0.2127)
+176.53
TOTAL
1,006.50
Add 15% CPOH on “Y”
+150.98
TOTAL
1,157.48
Add Cess @ 1% on “Z”
+11.57
Cost of 10.00 sqm
1,169.05
Cost of 1.00 sqm
116.91
SAY
₹116.90
D-02/SOURCEPRINTED PAGE 985
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
985

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 985. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.