CPWD Analysis of Rates · Finishing

Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour

New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre

Item number
13.41.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
7
Derived rate
185.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.41.1 Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour : New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre — is derived from 7 priced inputs for 10 sqm and works out to ₹185.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0808Water thinnable cement primer for interior wall surface, having VOC content less than 50 gram/litreWater thinnable cement primer for interior wall surface, having VOC content less than 50 grams/ litreMateriallitre0.740.0028.00
9988Sundries for brushes,sand paper & putty for filling holes including Carriage for primerMaterialL.S.8.062.2718.30
0802Acrylic distemper 1st quality , having VOC content less than 50 gram/ litreAcrylic distemper 1st quality , having VOC content less than 50 grams/ litreMaterialkilogram1.2545.0056.25
9988Sundries for brushes,sand paper including Carriage for distemperMaterialL.S.8.062.2718.30
0131PainterLabourday1816.00816.00
0115CoolieLabourday0.5736.00368.00
OtherNaN2.270.00
TOTAL
1,304.85
Add 1 % Water charges on “W”
13.05
TOTAL
1,317.90
Add GST on “X” (multiplying factor 0.2127)
280.32
TOTAL
1,598.22
Add 15% CPOH on “Y”
239.73
TOTAL
1,837.95
Add Cess @ 1% on “Z”
18.38
Cost of 10.00 sqm
1,856.33
Cost of 1.00 sqm
185.63
Say
185.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 985. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.