CPWD Analysis of Rates · Finishing
Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour
New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre
- Item number
- 13.41.1
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 7
- Derived rate
- ₹185.65 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.41.1 — Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour : New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre — is derived from 7 priced inputs for 10 sqm and works out to ₹185.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0808 | Water thinnable cement primer for interior wall surface, having VOC content less than 50 gram/litreWater thinnable cement primer for interior wall surface, having VOC content less than 50 grams/ litreMaterial | litre | 0.7 | 40.00 | 28.00 |
| 9988 | Sundries for brushes,sand paper & putty for filling holes including Carriage for primerMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0802 | Acrylic distemper 1st quality , having VOC content less than 50 gram/ litreAcrylic distemper 1st quality , having VOC content less than 50 grams/ litreMaterial | kilogram | 1.25 | 45.00 | 56.25 |
| 9988 | Sundries for brushes,sand paper including Carriage for distemperMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0131 | PainterLabour | day | 1 | 816.00 | 816.00 |
| 0115 | CoolieLabour | day | 0.5 | 736.00 | 368.00 |
| Other | NaN | 2.27 | 0.00 |
- TOTAL
- 1,304.85
- Add 1 % Water charges on “W”
- 13.05
- TOTAL
- 1,317.90
- Add GST on “X” (multiplying factor 0.2127)
- 280.32
- TOTAL
- 1,598.22
- Add 15% CPOH on “Y”
- 239.73
- TOTAL
- 1,837.95
- Add Cess @ 1% on “Z”
- 18.38
- Cost of 10.00 sqm
- 1,856.33
- Cost of 1.00 sqm
- 185.63
- Say
- 185.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 985. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works