Skip to main content
R/DAR 2023

Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade

New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)
Item number
13.47.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹171.10/ SQM
D-01/RATE ANALYSISITEM 13.47.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.47.1 (Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade: New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)) is derived from 7 priced inputs for 10 sqm and works out to ₹171.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.47.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8506MATPremium Acrylic exterior paintlitre1.43250.00357.50
0837MATAcrylic Exterior Primerlitre0.980.0072.00
9977MATCarriage of materialL.S.1.562.273.54
0131LABPainterday0.6816.00489.60
0115LABCoolieday0.3736.00220.80
0101LABBhistiday0.05816.0040.80
9999MATSundries for brushes,sand paper & putty for filling holes etcL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
1,202.54
Add 1 % Water charges on “W”
+12.03
TOTAL
1,214.57
Add GST on “X” (multiplying factor 0.2127)
+258.34
TOTAL
1,472.91
Add 15% CPOH on “Y”
+220.94
TOTAL
1,693.85
Add Cess @ 1% on “Z”
+16.94
Cost of 10.00 sqm
1,710.79
Cost of 1.00 sqm
171.08
SAY
₹171.10
D-02/SOURCEPRINTED PAGE 987
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
987

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 987. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.