CPWD Analysis of Rates · Finishing

Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement

Item number
13.20
Analysis basis
Detail of cost for 10 sqm
Priced inputs
19
Derived rate
829.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.20 Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement — is derived from 19 priced inputs for 10 sqm and works out to ₹829.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Under layer 12 mm thick cement plaster
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Top layer 10 mm thick cement plaster
  • Cement mortar 1 : 3 (1 cement : 3 fine
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.1444,211.70606.48
0155Mason (average)Labourday0.67857.00574.19
0114BeldarLabourday0.75736.00552.00
0101BhistiLabourday0.92816.00750.72
9999Scaffolding and sundriesMaterialL.S.9.882.2722.43
Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysiscum0.124,379.05525.49
0155Mason (average)Labourday0.61857.00522.77
0114BeldarLabourday0.69736.00507.84
0101BhistiLabourday0.85816.00693.60
9999Scaffolding and sundriesMaterialL.S.9.882.2722.43
1179Crushed stone 2.36 mm to 12.5 mm sizeMaterialcum0.11,005.00100.50
0101BhistiLabourday0.01816.008.16
0777Dry hydrated lime (factory made)Materialquintal0.09315.0028.35
9977Carriage of limeMaterialL.S.3.642.278.26
0155Mason (average)Labourday0.5857.00428.50
0114BeldarLabourday0.5736.00368.00
0101BhistiLabourday0.1816.0081.60
9999Scaffolding and sundriesMaterialL.S.9.882.2722.43
9999Scaffolding and sundriesMaterialL.S.4.422.2710.03
TOTAL
5,833.78
Add 1 % Water charges on “W”
58.34
TOTAL
5,892.12
Add GST on “X” (multiplying factor 0.2127)
1,253.25
TOTAL
7,145.37
Add 15% CPOH on “Y”
1,071.81
TOTAL
8,217.18
Add Cess @ 1% on “Z”
82.17
Cost of 10.00 sqm
8,299.35
Cost of 1.00 sqm
829.94
Say
829.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 968. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.