CPWD Analysis of Rates · Finishing
Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement
- Item number
- 13.20
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 19
- Derived rate
- ₹829.95 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.20 — Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement — is derived from 19 priced inputs for 10 sqm and works out to ₹829.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 12 mm thick cement plaster
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Top layer 10 mm thick cement plaster
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.144 | 4,211.70 | 606.48 | |
| 0155 | Mason (average)Labour | day | 0.67 | 857.00 | 574.19 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 0101 | BhistiLabour | day | 0.92 | 816.00 | 750.72 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.12 | 4,379.05 | 525.49 | |
| 0155 | Mason (average)Labour | day | 0.61 | 857.00 | 522.77 |
| 0114 | BeldarLabour | day | 0.69 | 736.00 | 507.84 |
| 0101 | BhistiLabour | day | 0.85 | 816.00 | 693.60 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 1179 | Crushed stone 2.36 mm to 12.5 mm sizeMaterial | cum | 0.1 | 1,005.00 | 100.50 |
| 0101 | BhistiLabour | day | 0.01 | 816.00 | 8.16 |
| 0777 | Dry hydrated lime (factory made)Material | quintal | 0.09 | 315.00 | 28.35 |
| 9977 | Carriage of limeMaterial | L.S. | 3.64 | 2.27 | 8.26 |
| 0155 | Mason (average)Labour | day | 0.5 | 857.00 | 428.50 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 0101 | BhistiLabour | day | 0.1 | 816.00 | 81.60 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 4.42 | 2.27 | 10.03 |
- TOTAL
- 5,833.78
- Add 1 % Water charges on “W”
- 58.34
- TOTAL
- 5,892.12
- Add GST on “X” (multiplying factor 0.2127)
- 1,253.25
- TOTAL
- 7,145.37
- Add 15% CPOH on “Y”
- 1,071.81
- TOTAL
- 8,217.18
- Add Cess @ 1% on “Z”
- 82.17
- Cost of 10.00 sqm
- 8,299.35
- Cost of 1.00 sqm
- 829.94
- Say
- 829.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 968. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works