Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement
- Item number
- 13.20
- Analysis basis
- 10 sqm
- Priced inputs
- 19
- Derived rate
- ₹829.95/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.20 (Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement) is derived from 19 priced inputs for 10 sqm and works out to ₹829.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 12 mm thick cement plaster
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Top layer 10 mm thick cement plaster
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.144 | 4,211.70 | 606.48 | |
| 0155 | LAB | Mason (average) | day | 0.67 | 857.00 | 574.19 |
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
| 0101 | LAB | Bhisti | day | 0.92 | 816.00 | 750.72 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 9.88 | 2.27 | 22.43 |
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.12 | 4,379.05 | 525.49 | |
| 0155 | LAB | Mason (average) | day | 0.61 | 857.00 | 522.77 |
| 0114 | LAB | Beldar | day | 0.69 | 736.00 | 507.84 |
| 0101 | LAB | Bhisti | day | 0.85 | 816.00 | 693.60 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 9.88 | 2.27 | 22.43 |
| 1179 | MAT | Crushed stone 2.36 mm to 12.5 mm size | cum | 0.1 | 1,005.00 | 100.50 |
| 0101 | LAB | Bhisti | day | 0.01 | 816.00 | 8.16 |
| 0777 | MAT | Dry hydrated lime (factory made) | quintal | 0.09 | 315.00 | 28.35 |
| 9977 | MAT | Carriage of lime | L.S. | 3.64 | 2.27 | 8.26 |
| 0155 | LAB | Mason (average) | day | 0.5 | 857.00 | 428.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 0101 | LAB | Bhisti | day | 0.1 | 816.00 | 81.60 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 9.88 | 2.27 | 22.43 |
| 9999 | MAT | Scaffolding and sundries | L.S. | 4.42 | 2.27 | 10.03 |
- TOTAL
- 5,833.78
- Add 1 % Water charges on “W”
- +58.34
- TOTAL
- 5,892.12
- Add GST on “X” (multiplying factor 0.2127)
- +1,253.25
- TOTAL
- 7,145.37
- Add 15% CPOH on “Y”
- +1,071.81
- TOTAL
- 8,217.18
- Add Cess @ 1% on “Z”
- +82.17
- Cost of 10.00 sqm
- 8,299.35
- Cost of 1.00 sqm
- 829.94
- SAY
- ₹829.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 968
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 968. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.