R/DAR 2023

Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers

Item number
13.21
Analysis basis
12mm cement
Priced inputs
2
Derived rate
₹22.10/ BAG OF 50 KG CEMENT USED IN THE MIX
D-01/RATE ANALYSISITEM 13.21

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.21 (Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers) is derived from 2 priced inputs for 12mm cement and works out to ₹22.10 per bag of 50 kg cement used in the mix after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (1 cement :3 sand) = 10 sqm or 1.47 bags
  • of cement used in the mix.
  • Cement required for 10 sqm =0.144x510=
  • 73.44kg.
  • Water proofing material required @0. 1 kg
  • per 50 kg of cement = 0.147 kg.
ANALYSIS OF RATES · ITEM 13.21DETAIL OF COST FOR 12MM CEMENT PLASTER 1:3
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1213MATWater proofing materialskilogram0.14745.006.62
9999MATSundriesL.S.7.152.2716.23
BUILD-UP TO RATE
TOTAL
22.85
Add 1 % Water charges on “W”
+0.23
TOTAL
23.08
Add GST on “X” (multiplying factor 0.2127)
+4.91
TOTAL
27.99
Add 15% CPOH on “Y”
+4.20
TOTAL
32.19
Add Cess @ 1% on “Z”
+0.32
Cost of 1.47 bags of cement used in the mix.
32.51
Cost of 1.00 bag of 50 kg cement used in the mix.
22.12
SAY
₹22.10
D-02/SOURCEPRINTED PAGE 969
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
969

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 969. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.