CPWD Analysis of Rates · Finishing
Rough cast plaster upto 10 m height above ground level with a mixture of sand and gravel or crushed stone from 6 mm to 10 mm nominal size, dashed over and including the fresh plaster in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement
Ordinary cement finish using ordinary cement
- Item number
- 13.19.1
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 20
- Derived rate
- ₹886.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.19.1 — Rough cast plaster upto 10 m height above ground level with a mixture of sand and gravel or crushed stone from 6 mm to 10 mm nominal size, dashed over and including the fresh plaster in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement Ordinary cement finish using ordinary cement — is derived from 20 priced inputs for 10 sqm and works out to ₹886.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 12 mm thick cement plaster
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Top layer 10 mm thick cement plaster
- Cement mortar 1 : 3 (1 cement : 3 fine
- sand)
- Labour for scooping
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.144 | 4,211.70 | 606.48 | |
| 0155 | Mason (average)Labour | day | 0.67 | 857.00 | 574.19 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 0101 | BhistiLabour | day | 0.92 | 816.00 | 750.72 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.12 | 4,379.05 | 525.49 | |
| 0155 | Mason (average)Labour | day | 0.61 | 857.00 | 522.77 |
| 0114 | BeldarLabour | day | 0.69 | 736.00 | 507.84 |
| 0101 | BhistiLabour | day | 0.85 | 816.00 | 693.60 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 1179 | Crushed stone 2.36 mm to 12.5 mm sizeMaterial | cum | 0.1 | 1,005.00 | 100.50 |
| 0101 | BhistiLabour | day | 0.01 | 816.00 | 8.16 |
| 0777 | Dry hydrated lime (factory made)Material | quintal | 0.09 | 315.00 | 28.35 |
| 9977 | Carriage of limeMaterial | L.S. | 3.64 | 2.27 | 8.26 |
| 0155 | Mason (average)Labour | day | 0.5 | 857.00 | 428.50 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 0101 | BhistiLabour | day | 0.1 | 816.00 | 81.60 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 9.88 | 2.27 | 22.43 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.25 | 897.00 | 224.25 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
- TOTAL
- 6,232.00
- Add 1 % Water charges on “W”
- 62.32
- TOTAL
- 6,294.32
- Add GST on “X” (multiplying factor 0.2127)
- 1,338.80
- TOTAL
- 7,633.12
- Add 15% CPOH on “Y”
- 1,144.97
- TOTAL
- 8,778.09
- Add Cess @ 1% on “Z”
- 87.78
- Cost of 10.00 sqm
- 8,865.87
- Cost of 1.00 sqm
- 886.59
- Say
- 886.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 967. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.