Rough cast plaster upto 10 m height above ground level with a mixture of sand and gravel or crushed stone from 6 mm to 10 mm nominal size, dashed over and including the fresh plaster in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement

Ordinary cement finish using ordinary cement
Item number
13.19.1
Analysis basis
10 sqm
Priced inputs
20
Derived rate
₹886.60/ SQM
D-01/RATE ANALYSISITEM 13.19.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.19.1 (Rough cast plaster upto 10 m height above ground level with a mixture of sand and gravel or crushed stone from 6 mm to 10 mm nominal size, dashed over and including the fresh plaster in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement Ordinary cement finish using ordinary cement) is derived from 20 priced inputs for 10 sqm and works out to ₹886.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Under layer 12 mm thick cement plaster
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Top layer 10 mm thick cement plaster
  • Cement mortar 1 : 3 (1 cement : 3 fine
  • sand)
  • Labour for scooping
ANALYSIS OF RATES · ITEM 13.19.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.1444,211.70606.48
0155LABMason (average)day0.67857.00574.19
0114LABBeldarday0.75736.00552.00
0101LABBhistiday0.92816.00750.72
9999MATScaffolding and sundriesL.S.9.882.2722.43
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.124,379.05525.49
0155LABMason (average)day0.61857.00522.77
0114LABBeldarday0.69736.00507.84
0101LABBhistiday0.85816.00693.60
9999MATScaffolding and sundriesL.S.9.882.2722.43
1179MATCrushed stone 2.36 mm to 12.5 mm sizecum0.11,005.00100.50
0101LABBhistiday0.01816.008.16
0777MATDry hydrated lime (factory made)quintal0.09315.0028.35
9977MATCarriage of limeL.S.3.642.278.26
0155LABMason (average)day0.5857.00428.50
0114LABBeldarday0.5736.00368.00
0101LABBhistiday0.1816.0081.60
9999MATScaffolding and sundriesL.S.9.882.2722.43
0123LABMason 1st classMason 1st classday0.25897.00224.25
0114LABBeldarday0.25736.00184.00
BUILD-UP TO RATE
TOTAL
6,232.00
Add 1 % Water charges on “W”
+62.32
TOTAL
6,294.32
Add GST on “X” (multiplying factor 0.2127)
+1,338.80
TOTAL
7,633.12
Add 15% CPOH on “Y”
+1,144.97
TOTAL
8,778.09
Add Cess @ 1% on “Z”
+87.78
Cost of 10.00 sqm
8,865.87
Cost of 1.00 sqm
886.59
SAY
₹886.60
D-02/SOURCEPRINTED PAGE 967
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
967

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 967. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.