Finishing walls with Acrylic Smooth exterior paint of required shade

Old work (One or more coat applied @ 0.90 ltr/10 sqm)
Item number
13.111.2
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹80.65/ SQM
D-01/RATE ANALYSISITEM 13.111.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.111.2 (Finishing walls with Acrylic Smooth exterior paint of required shade : Old work (One or more coat applied @ 0.90 ltr/10 sqm)) is derived from 5 priced inputs for 10 sqm and works out to ₹80.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.111.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8505MATAcrylic exterior paintlitre0.9170.00153.00
9977MATCarriage of materialL.S.0.522.271.18
0131LABPainterday0.33816.00269.28
0115LABCoolieday0.17736.00125.12
9999MATSundries for brushes,sand paper,scaffolding etcL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
566.88
Add 1 % Water charges on “W”
+5.67
TOTAL
572.55
Add GST on “X” (multiplying factor 0.2127)
+121.78
TOTAL
694.33
Add 15% CPOH on “Y”
+104.15
TOTAL
798.48
Add Cess @ 1% on “Z”
+7.98
Cost of 10.00 sqm
806.46
Cost of 1.00 sqm
80.65
SAY
₹80.65
D-02/SOURCEPRINTED PAGE 1031
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1031

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1031. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.