Finishing walls with Acrylic Smooth exterior paint of required shade

Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing cement paint surface
Item number
13.111.1
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹120.75/ SQM
D-01/RATE ANALYSISITEM 13.111.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.111.1 (Finishing walls with Acrylic Smooth exterior paint of required shade : Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing cement paint surface) is derived from 5 priced inputs for 10 sqm and works out to ₹120.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.111.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8505MATAcrylic exterior paintlitre1.67170.00283.90
9977MATCarriage of materialL.S.0.912.272.07
0131LABPainterday0.46816.00375.36
0115LABCoolieday0.23736.00169.28
9999MATSundries for brushes,sand paper,scaffolding etcL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
848.91
Add 1 % Water charges on “W”
+8.49
TOTAL
857.40
Add GST on “X” (multiplying factor 0.2127)
+182.37
TOTAL
1,039.77
Add 15% CPOH on “Y”
+155.97
TOTAL
1,195.74
Add Cess @ 1% on “Z”
+11.96
Cost of 10.00 sqm
1,207.70
Cost of 1.00 sqm
120.77
SAY
₹120.75
D-02/SOURCEPRINTED PAGE 1030
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1030

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1030. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.