Finishing walls with textured exterior paint of required shade
- Item number
- 13.110.2
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹109.10/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.110.2 (Finishing walls with textured exterior paint of required shade : Old work (One or more coats) applied @ 1.82 ltr/10 sqm) is derived from 6 priced inputs for 10 sqm and works out to ₹109.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8507 | MAT | Textured exterior paint | litre | 1.82 | 185.00 | 336.70 |
| 9977 | MAT | Carriage of material | L.S. | 0.52 | 2.27 | 1.18 |
| 0131 | LAB | Painter | day | 0.33 | 816.00 | 269.28 |
| 0115 | LAB | Coolie | day | 0.17 | 736.00 | 125.12 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 766.81
- Add 1 % Water charges on “W”
- +7.67
- TOTAL
- 774.48
- Add GST on “X” (multiplying factor 0.2127)
- +164.73
- TOTAL
- 939.21
- Add 15% CPOH on “Y”
- +140.88
- TOTAL
- 1,080.09
- Add Cess @ 1% on “Z”
- +10.80
- Cost of 10.00 sqm
- 1,090.89
- Cost of 1.00 sqm
- 109.09
- SAY
- ₹109.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1030
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1030. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.