Finishing walls with textured exterior paint of required shade
- Item number
- 13.110.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹169.20/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.110.1 (Finishing walls with textured exterior paint of required shade : Old work (Two or more coats on existing cement paint surface applied @ 3.28 ltr/10 sqm) is derived from 6 priced inputs for 10 sqm and works out to ₹169.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8507 | MAT | Textured exterior paint | litre | 3.28 | 185.00 | 606.80 |
| 9977 | MAT | Carriage of material | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | LAB | Painter | day | 0.46 | 816.00 | 375.36 |
| 0115 | LAB | Coolie | day | 0.23 | 736.00 | 169.28 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 1,189.51
- Add 1 % Water charges on “W”
- +11.90
- TOTAL
- 1,201.41
- Add GST on “X” (multiplying factor 0.2127)
- +255.54
- TOTAL
- 1,456.95
- Add 15% CPOH on “Y”
- +218.54
- TOTAL
- 1,675.49
- Add Cess @ 1% on “Z”
- +16.75
- Cost of 10.00 sqm
- 1,692.24
- Cost of 1.00 sqm
- 169.22
- SAY
- ₹169.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1029
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1029. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.