Finishing walls with water proofing cement paint of required shade

Old work (one or more coats @ 2.20 kg/10 sqm) complete
Item number
13.109.2
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹75.80/ SQM
D-01/RATE ANALYSISITEM 13.109.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.109.2 (Finishing walls with water proofing cement paint of required shade : Old work (one or more coats @ 2.20 kg/10 sqm) complete) is derived from 7 priced inputs for 10 sqm and works out to ₹75.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.109.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0851MATWater proofing cement paintkilogram2.241.0090.20
9977MATCarriage of materialL.S.1.12.272.50
0131LABPainterday0.35816.00285.60
0115LABCoolieday0.12736.0088.32
0101LABBhistiday0.05816.0040.80
9999MATBrushes, sand paper etcL.S.3.152.277.15
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
532.87
Add 1 % Water charges on “W”
+5.33
TOTAL
538.20
Add GST on “X” (multiplying factor 0.2127)
+114.48
TOTAL
652.68
Add 15% CPOH on “Y”
+97.90
TOTAL
750.58
Add Cess @ 1% on “Z”
+7.51
Cost of 10.00 sqm
758.09
Cost of 1.00 sqm
75.81
SAY
₹75.80
D-02/SOURCEPRINTED PAGE 1029
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1029

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1029. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.