Finishing walls with water proofing cement paint of required shade
- Item number
- 13.109.1
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹112.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.109.1 (Finishing walls with water proofing cement paint of required shade : Old work (one or more coats applied @ 2.20 kg/10 sqm) over priming coat of primer applied @ 0.80 litrs/10 sqm complete including cost of Priming coat) is derived from 8 priced inputs for 10 sqm and works out to ₹112.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0851 | MAT | Water proofing cement paint | kilogram | 2.2 | 41.00 | 90.20 |
| 8508 | MAT | Primer for cement paint | litre | 0.8 | 100.00 | 80.00 |
| 9977 | MAT | Carriage of material | L.S. | 1.56 | 2.27 | 3.54 |
| 0131 | LAB | Painter | day | 0.46 | 816.00 | 375.36 |
| 0115 | LAB | Coolie | day | 0.23 | 736.00 | 169.28 |
| 0101 | LAB | Bhisti | day | 0.05 | 816.00 | 40.80 |
| 9999 | MAT | Brushes, sand paper etc | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 793.71
- Add 1 % Water charges on “W”
- +7.94
- TOTAL
- 801.65
- Add GST on “X” (multiplying factor 0.2127)
- +170.51
- TOTAL
- 972.16
- Add 15% CPOH on “Y”
- +145.82
- TOTAL
- 1,117.98
- Add Cess @ 1% on “Z”
- +11.18
- Cost of 10.00 sqm
- 1,129.16
- Cost of 1.00 sqm
- 112.92
- SAY
- ₹112.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1028
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1028. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.