Finishing walls with water proofing cement paint of required shade

Old work (one or more coats applied @ 2.20 kg/10 sqm) over priming coat of primer applied @ 0.80 litrs/10 sqm complete including cost of Priming coat
Item number
13.109.1
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹112.90/ SQM
D-01/RATE ANALYSISITEM 13.109.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.109.1 (Finishing walls with water proofing cement paint of required shade : Old work (one or more coats applied @ 2.20 kg/10 sqm) over priming coat of primer applied @ 0.80 litrs/10 sqm complete including cost of Priming coat) is derived from 8 priced inputs for 10 sqm and works out to ₹112.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.109.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0851MATWater proofing cement paintkilogram2.241.0090.20
8508MATPrimer for cement paintlitre0.8100.0080.00
9977MATCarriage of materialL.S.1.562.273.54
0131LABPainterday0.46816.00375.36
0115LABCoolieday0.23736.00169.28
0101LABBhistiday0.05816.0040.80
9999MATBrushes, sand paper etcL.S.7.152.2716.23
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
793.71
Add 1 % Water charges on “W”
+7.94
TOTAL
801.65
Add GST on “X” (multiplying factor 0.2127)
+170.51
TOTAL
972.16
Add 15% CPOH on “Y”
+145.82
TOTAL
1,117.98
Add Cess @ 1% on “Z”
+11.18
Cost of 10.00 sqm
1,129.16
Cost of 1.00 sqm
112.92
SAY
₹112.90
D-02/SOURCEPRINTED PAGE 1028
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1028

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1028. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.